Bishkek, Nov. 20, 2020. /Kabar/. Energy companies are ready for 2020-2021 autumn-winter period, Chairman of the Board of the National Energy Holding of the Kyrgyz Republic Nurbek Kozubekov said during a press conference at Kabar News Agency.
According to him, as of Nov. 20, the rest of coal in the warehouse of the Bishkek Thermal Power Station is 299.1 thousand tons of fuel.
"67 thousand tons of Kazakhstani coal, 326 thousand tons of Kara-Keche coal and 29 thousand tons of Tash-Kumyr coal were imported.
Also, fuel oil in the volume of 20 thousand tons was prepared for Osh city Thermal Power Station according to contract concluded with Kyrgyzneftegaz OJSC.
He noted that repairs of 110-220-500 kV power transmission lines with the length of 396 km and two transformers with the total capacity of 63 MVA have been performed.